| ID |
Name |
Duration |
Start |
Finish |
Actual Start |
Actual Finish |
Resource Names |
| 1 | Illinois FCC Field Test | 139.00d | 4/8/97 | 10/17/97 | 4/8/97 | NA | SPOC Team |
| 2 | __FCC Field Test Topography | 77.00d | 4/8/97 | 7/23/97 | 4/8/97 | NA | SPOC Team |
| 3 | ____Each Participating Company to Identify their SPOC | 1.00d | 4/8/97 | 4/8/97 | 4/8/97 | NA | SPOC Team |
| 12 | ____Order Circuits to NPAC | 60.00d | 4/8/97 | 6/30/97 | NA | NA | SPOC Team |
| 13 | ______Order Ameritech Circuits | 0.00d | 6/11/97 | 6/11/97 | 6/11/97 | 6/11/97 | Bob |
| 14 | ______Order AT&T Circuits | 60.00d | 4/8/97 | 6/30/97 | NA | NA | Eileen |
| 15 | ______Order MCI Circuits | 60.00d | 4/8/97 | 6/30/97 | NA | NA | Hamp |
| 16 | ______Order SPRINT Circuits | 60.00d | 4/8/97 | 6/30/97 | NA | NA | Larry |
| 17 | ______Order TCG Circuits | 60.00d | 4/8/97 | 6/30/97 | NA | NA | Rajeev |
| 18 | ______Order WorldCom Circuits | 60.00d | 4/8/97 | 6/30/97 | NA | NA | Mitch |
| 19 | ____Install and Test Circuits | 22.00d | 6/12/97 | 7/11/97 | 6/12/97 | NA | SPOC Team |
| 20 | ______Install Ameritech Circuits | 1.00d | 6/12/97 | 6/12/97 | 6/12/97 | 6/12/97 | Bob |
| 21 | ______Install AT&T Circuits | 10.00d | 6/30/97 | 7/11/97 | NA | NA | Eileen |
| 22 | ______Install MCI Circuits | 10.00d | 6/30/97 | 7/11/97 | NA | NA | Hamp |
| 23 | ______Install SPRINT Circuits | 10.00d | 6/30/97 | 7/11/97 | NA | NA | Larry |
| 24 | ______Install TCG Circuits | 10.00d | 6/30/97 | 7/11/97 | NA | NA | Rajeev |
| 25 | ______Install WorldCom Circuits | 10.00d | 6/30/97 | 7/11/97 | NA | NA | Mitch |
| 26 | ____Determine Topography for Testing | 59.00d | 4/8/97 | 6/28/97 | 4/17/97 | NA | SPOC Team |
| 27 | ______Each Service Provider to Identify their Network Topography | 13.00d | 4/8/97 | 4/24/97 | 4/17/97 | NA | SPOC Team |
| 35 | ______SPOC Team to combine Network Topography's | 2.00d | 4/17/97 | 4/18/97 | 4/17/97 | 4/18/97 | SPOC Team |
| 36 | ______Determine which Interconnection Agreements need to be in place | 1.00d | 4/18/97 | 4/19/97 | 4/18/97 | 4/19/97 | SPOC Team |
| 37 | ______Testing Interconnection agreement in place for FCC Field Test | 1.00d | 4/20/97 | 4/21/97 | 4/20/97 | 4/21/97 | SPOC Team |
| 38 | ______Determine NPA-NXXs to be opened | 1.00d | 4/23/97 | 4/23/97 | 4/23/97 | 4/23/97 | SPOC Team |
| 39 | ________Ameritech NPA-NXXs | 1.00d | 4/23/97 | 4/23/97 | 4/23/97 | 4/23/97 | Bob |
| 40 | ________AT&T NPA-NXXs | 1.00d | 4/23/97 | 4/23/97 | 4/23/97 | 4/23/97 | Eileen |
| 41 | ________MCI NPA-NXXs | 1.00d | 4/23/97 | 4/23/97 | 4/23/97 | 4/23/97 | Hamp |
| 42 | ________SPRINT NPA-NXXs | 1.00d | 4/23/97 | 4/23/97 | 4/23/97 | 4/23/97 | Larry |
| 43 | ________TCG NPA-NXXs | 1.00d | 4/23/97 | 4/23/97 | 4/23/97 | 4/23/97 | Rajeev |
| 44 | ________WorldCom NPA-NXXs | 1.00d | 4/23/97 | 4/23/97 | 4/23/97 | 4/23/97 | Mitch |
| 45 | ______Determine SSNs | 1.00d | 4/24/97 | 4/24/97 | 4/24/97 | 4/24/97 | SPOC Team |
| 46 | ________Ameritech SSNs | 1.00d | 4/24/97 | 4/24/97 | 4/24/97 | 4/24/97 | Bob |
| 47 | ________AT&T SSNs | 1.00d | 4/24/97 | 4/24/97 | 4/24/97 | 4/24/97 | Eileen |
| 48 | ________MCI SSNs | 1.00d | 4/24/97 | 4/24/97 | 4/24/97 | 4/24/97 | Hamp |
| 49 | ________SPRINT SSNs | 1.00d | 4/24/97 | 4/24/97 | 4/24/97 | 4/24/97 | Larry |
| 50 | ________TCG SSNs | 1.00d | 4/24/97 | 4/24/97 | 4/24/97 | 4/24/97 | Rajeev |
| 51 | ________WorldCom SSNs | 1.00d | 4/24/97 | 4/24/97 | 4/24/97 | 4/24/97 | Mitch |
| 52 | ______Determine Phone Numbers | 0.00d | 5/25/97 | 5/25/97 | 5/25/97 | 5/25/97 | SPOC Team |
| 53 | ________Ameritech PNs | 0.00d | 5/25/97 | 5/25/97 | 5/25/97 | 5/25/97 | Bob |
| 54 | ________AT&T PNs | 0.00d | 5/25/97 | 5/25/97 | 5/25/97 | 5/25/97 | Eileen |
| 55 | ________MCI PNs | 0.00d | 5/25/97 | 5/25/97 | 5/25/97 | 5/25/97 | Hamp |
| 56 | ________SPRINT PNs | 0.00d | 5/25/97 | 5/25/97 | 5/25/97 | 5/25/97 | Larry |
| 57 | ________TCG PNs | 0.00d | 5/25/97 | 5/25/97 | 5/25/97 | 5/25/97 | Rajeev |
| 58 | ________WorldCom PNs | 0.00d | 5/25/97 | 5/25/97 | 5/25/97 | 5/25/97 | Mitch |
| 59 | ______Determine Point Codes | 23.00d | 5/28/97 | 6/28/97 | 5/28/97 | 6/28/97 | SPOC Team |
| 60 | ________Ameritech Point Codes | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Bob |
| 61 | ________AT&T Point Codes | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Eileen |
| 62 | ________MCI Point Codes | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Hamp |
| 63 | ________SPRINT Point Codes | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Larry |
| 64 | ________TCG Point Codes | 23.00d | 5/28/97 | 6/28/97 | 5/28/97 | 6/28/97 | Rajeev |
| 65 | ________WorldCom Point Codes | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Mitch |
| 66 | ______Determine Alias Point Codes | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | NA | SPOC Team |
| 67 | ________Ameritech APC | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Bob |
| 68 | ________At&t APC | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Eileen |
| 69 | ________MCI APC | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Hamp |
| 70 | ________SPRINT APC | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Larry |
| 71 | ________TCG APC | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | NA | Rajeev |
| 72 | ________WorldCom APC | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Mitch |
| 73 | ______Determine TTNs | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | SPOC Team |
| 74 | ________Ameritech TTNs | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Bob |
| 75 | ________AT&T TTNs | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Eileen |
| 76 | ________MCI TTNs | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Hamp |
| 77 | ________SPRINT TTNs | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Larry |
| 78 | ________TCG TTNs | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Rajeev |
| 79 | ________WorldCom TTNs | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Mitch |
| 80 | ______SPOC's Establish Testing Task Force | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | SPOC Team |
| 81 | ________Ameritech Task Force | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Bob |
| 82 | ________AT&T Task Force | 0.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Eileen |
| 83 | ________MCI Task Force | 0.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Hamp |
| 84 | ________SPRINT Task Force | 0.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Larry |
| 85 | ________TCG Task Force | 0.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Rajeev |
| 86 | ________WorldCom Task Force | 0.00d | 5/28/97 | 5/28/97 | 5/28/97 | 5/28/97 | Mitch |
| 87 | ____FCC Field Test SP DATA | 30.00d | 6/12/97 | 7/23/97 | 6/12/97 | NA | SPOC Team |
| 88 | ______Ameritech SP Data | 1.00d | 6/12/97 | 6/12/97 | 6/12/97 | 6/12/97 | Bob |
| 89 | ______AT&T SP Data | 1.00d | 7/23/97 | 7/23/97 | NA | NA | Eileen |
| 90 | ______MCI SP Data | 1.00d | 7/23/97 | 7/23/97 | NA | NA | Hamp |
| 91 | ______SPRINT SP Data | 1.00d | 7/23/97 | 7/23/97 | NA | NA | Larry |
| 92 | ______TCG SP Data | 1.00d | 7/23/97 | 7/23/97 | NA | NA | Rajeev |
| 93 | ______WorldCom SP Data | 1.00d | 7/23/97 | 7/23/97 | NA | NA | Mitch |
| 94 | ____Each SPOC to determine which tests they will perform | 12.00d | 5/28/97 | 6/12/97 | 5/28/97 | NA | SPOC Team |
| 95 | ______Ameritech Test Selection | 12.00d | 5/28/97 | 6/12/97 | 5/28/97 | 6/12/97 | Bob |
| 96 | ______AT&T Test Selection | 12.00d | 5/28/97 | 6/12/97 | 5/28/97 | 6/12/97 | Eileen |
| 97 | ______MCI Test Selection | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | NA | Hamp |
| 98 | ______SPRINT Test Selection | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | NA | Larry |
| 99 | ______TCG Test Selection | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | NA | Rajeev |
| 100 | ______WorldCom Test Selection | 1.00d | 5/28/97 | 5/28/97 | 5/28/97 | NA | Mitch |
| 101 | ____Matrix of FCC Field Test Scripts | 1.00d | 6/12/97 | 6/12/97 | 6/12/97 | 6/12/97 | Dick Dowd Bill Belshaw |
| 102 | __Submit registration to LHM NPAC for inter-connection | 20.00d | 6/12/97 | 7/9/97 | 6/12/97 | NA | SPOC Team |
| 103 | ____Ameritech registration | 1.00d | 6/12/97 | 6/12/97 | 6/12/97 | 6/12/97 | Bob |
| 104 | ____AT&T registration | 1.00d | 7/9/97 | 7/9/97 | NA | NA | Eileen |
| 105 | ____MCI registration | 1.00d | 7/9/97 | 7/9/97 | NA | NA | Hamp |
| 106 | ____SPRINT registration | 1.00d | 7/9/97 | 7/9/97 | NA | NA | Larry |
| 107 | ____TCG registration | 1.00d | 7/9/97 | 7/9/97 | NA | NA | Rajeev |
| 108 | ____WorldCom registration | 1.00d | 7/9/97 | 7/9/97 | NA | NA | Mitch |
| 109 | __Trunking In Place to support Test | 2.00d | 7/14/97 | 7/15/97 | NA | NA | SPOC Team |
| 110 | ____Trunking In Place for 911 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | SPOC Team |
| 111 | ______Ameritech 911 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Bob |
| 112 | ______AT&T 911 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Eileen |
| 113 | ______MCI 911 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Hamp |
| 114 | ______SPRINT 911 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Larry |
| 115 | ______TCG 911 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Rajeev |
| 116 | ______WorldCom 911 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Mitch |
| 117 | ____Extracts to 911 DB | 1.00d | 7/15/97 | 7/15/97 | NA | NA | SPOC Team |
| 118 | ______Ameritech Ext | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Bob |
| 119 | ______AT&T Ext | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Eileen |
| 120 | ______MCI Ext | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Hamp |
| 121 | ______SPRINT Ext | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Larry |
| 122 | ______TCG Ext | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Rajeev |
| 123 | ______WorldCom Ext | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Mitch |
| 124 | ____SS7 Interconnection | 2.00d | 7/14/97 | 7/15/97 | NA | NA | SPOC Team |
| 125 | ______Ameritech SS7 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Bob |
| 126 | ______AT&T SS7 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Eileen |
| 127 | ______MCI SS7 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Hamp |
| 128 | ______SPRINT SS7 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Larry |
| 129 | ______TCG SS7 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Rajeev |
| 130 | ______WorldCom SS7 | 1.00d | 7/14/97 | 7/14/97 | NA | NA | Mitch |
| 131 | ______Pass Message sets Check LIDB & Calling Name | 1.00d | 7/15/97 | 7/15/97 | NA | NA | |
| 132 | ________Ameritech Msg | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Bob |
| 133 | ________AT&T Msg | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Eileen |
| 134 | ________MCI Msg | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Hamp |
| 135 | ________SPRINT Msg | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Larry |
| 136 | ________TCG Msg | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Rajeev |
| 137 | ________WorldCom Msg | 1.00d | 7/15/97 | 7/15/97 | NA | NA | Mitch |
| 138 | __Place order to open NPA-NXXs | 1.00d | 5/30/97 | 5/30/97 | 5/30/97 | 5/30/97 | |
| 139 | ____Ameritech order | 1.00d | 5/30/97 | 5/30/97 | 5/30/97 | 5/30/97 | Bob |
| 140 | ____AT&T order | 1.00d | 5/30/97 | 5/30/97 | 5/30/97 | 5/30/97 | Eileen |
| 141 | ____MCI order | 1.00d | 5/30/97 | 5/30/97 | 5/30/97 | 5/30/97 | Hamp |
| 142 | ____SPRINT order | 1.00d | 5/30/97 | 5/30/97 | 5/30/97 | 5/30/97 | Larry |
| 143 | ____TCG order | 1.00d | 5/30/97 | 5/30/97 | 5/30/97 | 5/30/97 | Rajeev |
| 144 | ____WorkdCom order | 1.00d | 5/30/97 | 5/30/97 | 5/30/97 | 5/30/97 | Mitch |
| 145 | __Test Customer Setup | 1.00d | 4/8/97 | 4/8/97 | NA | NA | |
| 146 | ____Ameritech CS | 1.00d | 4/8/97 | 4/8/97 | NA | NA | Bob |
| 147 | ____AT&T CS | 1.00d | 4/8/97 | 4/8/97 | NA | NA | Eileen |
| 148 | ____MCI CS | 1.00d | 4/8/97 | 4/8/97 | NA | NA | Hamp |
| 149 | ____SPRINT CS | 1.00d | 4/8/97 | 4/8/97 | NA | NA | Larry |
| 150 | ____TCG CS | 1.00d | 4/8/97 | 4/8/97 | NA | NA | Rajeev |
| 151 | ____WorldCom CS | 1.00d | 4/8/97 | 4/8/97 | NA | NA | Mitch |
| 152 | __Data Base Clean Up | 7.00d | 7/16/97 | 7/24/97 | NA | NA | NPAC/SMS COMMITTEE |
| 153 | __FCC FIELD TEST | 62.00d | 7/24/97 | 10/17/97 | NA | NA | Dick Dowd & SPOC Team |
| 154 | ____Submit LSRs to Port | 5.00d | 7/24/97 | 7/30/97 | NA | NA | SPOC Team |
| 155 | ______Ameritech LSRs | 5.00d | 7/24/97 | 7/30/97 | NA | NA | Bob |
| 156 | ______AT&T LSRs | 5.00d | 7/24/97 | 7/30/97 | NA | NA | Eileen |
| 157 | ______MCI LSRs | 5.00d | 7/24/97 | 7/30/97 | NA | NA | Hamp |
| 158 | ______SPRINT LSRs | 5.00d | 7/24/97 | 7/30/97 | NA | NA | Larry |
| 159 | ______TCG LSRs | 5.00d | 7/24/97 | 7/30/97 | NA | NA | Rajeev |
| 160 | ____Port first phone numbers | 1.00d | 7/31/97 | 7/31/97 | NA | NA | SPOC Team |
| 161 | ______Ameritech Ports | 1.00d | 7/31/97 | 7/31/97 | NA | NA | Bob |
| 162 | ______AT&T Ports | 1.00d | 7/31/97 | 7/31/97 | NA | NA | Eileen |
| 163 | ______MCI Ports | 1.00d | 7/31/97 | 7/31/97 | NA | NA | Hamp |
| 164 | ______SPRINT Ports | 1.00d | 7/31/97 | 7/31/97 | NA | NA | Larry |
| 165 | ______TCG Ports | 1.00d | 7/31/97 | 7/31/97 | NA | NA | Rajeev |
| 166 | ____SPs Perform First battery of Tests | 5.00d | 7/31/97 | 8/6/97 | NA | NA | SPOC Team |
| 167 | ______Ameritech FBTs | 5.00d | 7/31/97 | 8/6/97 | NA | NA | Bob |
| 168 | ______AT&T FBTs | 5.00d | 7/31/97 | 8/6/97 | NA | NA | Eileen |
| 169 | ______MCI FBTs | 5.00d | 7/31/97 | 8/6/97 | NA | NA | Hamp |
| 170 | ______SPRINT FBTs | 5.00d | 7/31/97 | 8/6/97 | NA | NA | Larry |
| 171 | ______TCG FBTs | 5.00d | 7/31/97 | 8/6/97 | NA | NA | Rajeev |
| 172 | ____Place LSRs for Second porting | 5.00d | 8/11/97 | 8/15/97 | NA | NA | SPOC Team |
| 173 | ______Ameritech LSRs | 3.00d | 8/11/97 | 8/13/97 | NA | NA | Bob |
| 174 | ______AT&T LSRs | 3.00d | 8/11/97 | 8/13/97 | NA | NA | Eileen |
| 175 | ______MCI LSRs | 3.00d | 8/11/97 | 8/13/97 | NA | NA | Hamp |
| 176 | ______SPRINT LSRs | 3.00d | 8/11/97 | 8/13/97 | NA | NA | Larry |
| 177 | ______TCG LSRs | 3.00d | 8/11/97 | 8/13/97 | NA | NA | Rajeev |
| 178 | ______WorldCom LSRs | 5.00d | 8/11/97 | 8/15/97 | NA | NA | Mitch |
| 179 | ____Second Porting of TNs | 1.00d | 8/18/97 | 8/18/97 | NA | NA | SPOC Team |
| 180 | ______Ameritech Second port | 1.00d | 8/18/97 | 8/18/97 | NA | NA | Bob |
| 181 | ______AT&T Second port | 1.00d | 8/18/97 | 8/18/97 | NA | NA | Eileen |
| 182 | ______MCI Second port | 1.00d | 8/18/97 | 8/18/97 | NA | NA | Hamp |
| 183 | ______SPRINT Second port | 1.00d | 8/18/97 | 8/18/97 | NA | NA | Larry |
| 184 | ______TCG Second port | 1.00d | 8/18/97 | 8/18/97 | NA | NA | Rajeev |
| 185 | ______WorldCom port | 1.00d | 8/18/97 | 8/18/97 | NA | NA | Mitch |
| 186 | ____SPs perform Second battery of tests | 20.00d | 8/19/97 | 9/15/97 | NA | NA | SPOC Team |
| 187 | ______Ameritech SBTs | 20.00d | 8/19/97 | 9/15/97 | NA | NA | Bob |
| 188 | ______AT&T SBTs | 20.00d | 8/19/97 | 9/15/97 | NA | NA | Eileen |
| 189 | ______MCI SBTs | 20.00d | 8/19/97 | 9/15/97 | NA | NA | Hamp |
| 190 | ______SPRINT SBTs | 20.00d | 8/19/97 | 9/15/97 | NA | NA | Larry |
| 191 | ______TCG SBTs | 20.00d | 8/19/97 | 9/15/97 | NA | NA | Rajeev |
| 192 | ______WorldCom FBTs | 20.00d | 8/19/97 | 9/15/97 | NA | NA | Mitch |
| 193 | ____Port back to Original | 24.00d | 9/16/97 | 10/17/97 | NA | NA | SPOC Team |
| 194 | ______Place LSR to Port Home | 5.00d | 9/16/97 | 9/22/97 | NA | NA | SPOC Team |
| 195 | ________Ameritech Place LSR | 5.00d | 9/16/97 | 9/22/97 | NA | NA | Bob |
| 196 | ________AT&T Place LSR | 5.00d | 9/16/97 | 9/22/97 | NA | NA | Eileen |
| 197 | ________MCI Place LSR | 5.00d | 9/16/97 | 9/22/97 | NA | NA | Hamp |
| 198 | ________SPRINT Place LSR | 5.00d | 9/16/97 | 9/22/97 | NA | NA | Larry |
| 199 | ________TCG Place LSR | 5.00d | 9/16/97 | 9/22/97 | NA | NA | Rajeev |
| 200 | ________WorldCom Place LSR | 5.00d | 9/16/97 | 9/22/97 | NA | NA | Mitch |
| 201 | ______Service Providers confirm numbers are back | 4.00d | 9/23/97 | 9/26/97 | NA | NA | SPOC Team |
| 202 | ________Ameritech Homed | 4.00d | 9/23/97 | 9/26/97 | NA | NA | Bob |
| 203 | ________AT&T Homed | 4.00d | 9/23/97 | 9/26/97 | NA | NA | Eileen |
| 204 | ________MCI Homed | 4.00d | 9/23/97 | 9/26/97 | NA | NA | Hamp |
| 205 | ________SPRING Homed | 4.00d | 9/23/97 | 9/26/97 | NA | NA | Larry |
| 206 | ________TCG Homed | 4.00d | 9/23/97 | 9/26/97 | NA | NA | Rajeev |
| 207 | ________WorldCom Homed | 4.00d | 9/23/97 | 9/26/97 | NA | NA | Mitch |
| 208 | ______Draft of FCC Field Test Report Review | 1.00d | 10/10/97 | 10/10/97 | NA | NA | Testing Committee |
| 209 | ______Final FCC Field Test Report Review | 1.00d | 10/15/97 | 10/15/97 | NA | NA | Testing Committee |
| 210 | ______FCC Field Test Report due to FCC | 2.00d | 10/16/97 | 10/17/97 | NA | NA | Steering Committee |